Baseline Schedulytics reads a baseline .xer file and produces a full DCMA 14-point assessment plus 10 extended quality checks, and Monte Carlo risk audit — as Word audit narratives, Excel analysis matrices, and interactive HTML dashboards you can hand straight to your PMO or client.
The app is a free download and includes a full 30-day evaluation trial. A permanent licence key unlocks clean, unwatermarked audit deliverables.
Planning engineers, project controls engineers, PMO teams, consultants, and contractors who need to validate a P6 baseline submittal, whether it's your own schedule before submission or a contractor's baseline you're reviewing on someone else's behalf.
An honest score out of 14: checks that need progress data show N/A on a baseline instead of a free pass. Plus dangling and circular logic, LOE, constraints on the critical path and repeated activities.
Choose DCMA Default, Owner / PMO (stricter) or EPC Contractor (relaxed). The profile is printed in the report, so nobody can claim the goalposts moved.
Generates completion confidence curves and sensitivity tornado charts to identify highest-risk critical path drivers.
Word review report with a Basis of Assessment appendix, a 15-sheet Excel workbook, and a standalone HTML dashboard with an SVG Gantt.
Interactive tree explorer allowing instant drilldown into individual WBS elements to verify predecessor and successor logic.
Zero cloud uploads. All calculations run strictly in your local workstation RAM, ensuring 100% NDA compliance for EPC mega-projects.
Load every contractor's baseline XER together. Packages are merged into one project network, cross-file logic links are honoured, and package becomes a filter across every view.
See when each package delivers Engineering, Procurement, Construction and Testing & Commissioning, how far apart they are, and why the trailing package trails.
Shows which package owns the path to project completion and ranks packages by exposure × influence, so you know who to follow up first.
A graded health score per package, plus the boundary defects that pass inside each package but fail once the packages are merged.
Eight project-level risks (R1–R8) with recommended actions, an interface register and a discipline-by-package cross matrix.
Station, area, discipline and work-package codes already in your XER drive the groupings, plus a combined baseline S-curve for the whole project.
Visual risk heatmap generated from P6 activity relationships. Click any tile to inspect.
| Audit Check | Standard | Civil (Pkg 1) | Structural (Pkg 2) | MEP (Pkg 3) | Commissioning | Project Total |
|---|---|---|---|---|---|---|
| DCMA #01 Missing Logic (No Pred/Succ) | < 5.0% | 1.2% |
3.4% |
8.1% |
0.5% |
3.3% |
| DCMA #02 Leads (Negative Lags) | 0.0% | 0.0% |
0.0% |
0.0% |
0.0% |
0.0% |
| DCMA #03 Excessive Lags (> 5 Days) | < 5.0% | 2.1% |
4.8% |
16.4% |
3.1% |
6.6% |
| DCMA #05 Hard Constraints (Mandatory) | < 5.0% | 0.8% |
1.5% |
7.2% |
1.0% |
2.6% |
| DCMA #06 High Total Float (> 44 Days) | < 5.0% | 3.2% |
4.1% |
12.8% |
2.5% |
5.6% |
| DCMA #07 Negative Total Float | 0.0% | 0.0% |
0.0% |
-14 d |
0.0% |
BREACH |
| DCMA #10 Critical Path Continuity | Pass | PASS |
PASS |
BROKEN |
PASS |
FAIL |
Each solid colored cell represents exact compliance risk. Baseline Schedulytics audits your .XER baseline and pinpoints offending activities instantly.
Explore the baseline health check results, logic checks, and audit deliverable summaries.
DCMA 14-point compliance scoring with extended quality checks, duration anomaly profiles, and submittal audit summary.
Drill down into individual work breakdown structures to isolate logic breaks, missing predecessors, and hard constraints.
Driving critical path continuity validation, high float thresholds, and negative float anomaly map.
High-speed baseline XER ingestion interface generating Word, Excel, and HTML reports completely offline.
Perpetual node-locked license. Download and evaluate against real baseline schedules during your trial period. Activate directly within the app or via the checkout page to unlock clean presentation deliverables.